USAID Energy Security Project

Commenced 06-2024 Delivered 01-2025

Supply of 2-off 25 MVA 110/35/10 kV for national grid operator. Terms: delivery at place and unloading.

As part of the USAID Energy Security Project, ELTEC Green Energy successfully executed the supply of two 25 MVA 110/35/10 kV power transformers for integration into the national grid infrastructure.

This project involved the manufacture, delivery, and unloading of high-voltage transformers, tailored to the specifications of the national grid operator. The equipment enhances regional energy resilience and supports Ukraine’s commitment to modernizing its electricity transmission systems.

  • Scope: Supply and logistics of 2×25 MVA 110/35/10 kV transformers
  • Terms: Delivery at place (DAP) with full unloading service
  • Commencement: June 2024
  • Delivery Completed: January 2025

This milestone reflects our continued dedication to supporting critical infrastructure projects, ensuring timely delivery and technical precision for partners in energy transition.